Regent 88 | October Construction Update

Published: 6 November 2017

Regent 88 | October Construction Update

Construction on Regent 88 is now well underway. Construction has been delayed as a result of changes having to be made to; the windows, steel and subsequently the services of the building. However, all changes which have been made will benefit the investor and users.

The windows have been changed by making the frame smaller, meaning the glass fabrication size will increase. This will benefit the users through the glass now being at desk level and them therefore having a clearer view to overlook.

Internally, the steel structures also needed to be re-installed and have now been completed. When the steel was being changed the service work also had to be removed. Service work was being re-installed seamlessly when the windows were being put in and is now being finalised, along with all external work.

Don’t hesitate to talk to a member of our consultants team for any more information on +44 (0) 161 337 3890, or email enquiries@hopwoodhouse.com.

Back to News

As Seen On

logos

As Seen On

Join our exclusive Investor Club to receive new product launches, articles and the monthly newsletter.

Join our Newsletter.

Need some help? Request a FREE call back today.

Whether you're a seasoned investor or considering your first property investment, our experienced team are here to help. Arrange a FREE call back from one of our team!

Free Call Back

Call our team today on +44 (0) 161 337 3890

Hopwood House - Property Investment